New York’s education department lags in school building reviews

Date:

Share post:

The State Education Department has a perpetual backlog of school building project reviews, with nearly half taking six months or longer before they are approved.

Of the hundreds of projects submitted for approval by SED, many typically languish for months, adding inflationary costs and impacting the way districts plan for things such as building renovations, new construction or modernizing structures for 21st century technology.

The SED unit that reviews building projects, the Facilities Planning Bureau, also uses 30-year-old technology and, at the time of the audit, had almost half of key reviewer jobs unfilled. The result is that school districts must wait for extended periods before they get state approval to start new construction projects.

The Always-On Insight and Networking Platform for Superintendents and Their Teams

AI-driven insights peer-to-peer collaboration and more build exclusively for K-12 Superintendents and thier leaders
Built for the uniqueness of the superintendent role and their supporting team.Most platforms treat all K–12 leaders the same. DA+ recognizes that superintendents face a unique level of pressure, complexity, visibility, and responsibility—and gives them a space designed specifically for the demands of the top job.
A community where you don’t have to explain the context.Skip the backstory. DA+ understands the job, the politics, the stakes, and the pace.
Your decisions shape communities.Find the tools and peer insight to make them with confidence here.
Leadership tailored to the realities of running a district.From board relations to budgets, crisis response to community trust—DA+ focuses on the challenges only superintendents navigate each day.
Built for superintendents.Powered by superintendents. Trusted by superintendents. If you run a district, you belong here.

Related Articles